Construction is well underway for ÑÇÖÞ³ÉÈËÊÓÆµ’s new mass timber, zero carbon and LEED platinum building that uses geothermal heating and cooling as well as rooftop photovoltaics and an underground cistern for rainwater collection and reuse. The Lawson Centre for Sustainability will provide critical residential, academic and community spaces for the community, and features a rooftop farm and a community kitchen to make sustainability part of daily life at the College.
![]() |
December 5, 2025: Marking another milestone – building signage was installed along Devonshire Place on December 3! Did you know: The main entrance area provides direct barrier-free access to the new building and connectivity to the Gerald Larkin Building and George Ignatieff Theatre. |
![]() |
November 28, 2025: Leading Sustainability Through Innovation Trinity’s building contractor Graham Construction’s Sean Carroll discusses the of the Lawson Centre for Sustainability. (Photos: aerial views of the new building by Sean Carroll)) |
![]() |
November 5, 2025: Along Devonshire Place, the main entrance to the Lawson Centre for Sustainability is taking shape! Once complete, this work will provide direct barrier-free access to the new building and connectivity to the Gerald Larkin Building and George Ignatieff Theatre. |
![]() |
October 24, 2025: Work continues on the new Garden Courtyard, with landscaping designed to feature drought-tolerant and native species that encourage biodiversity. THEN (left: render by Mecanoo) and NOW (right: October 22). |
![]() |
October 17, 2025: Progress continues in the Centre Wing (Nevil Thomas Wing) of the Lawson Centre for Sustainability. In the new dining hall, crews are actively installing flooring, wall protection, and wall tiles in preparation for the next phase, which includes setting up food stations, kitchen equipment, and painting. On level two, millwork is being installed in the common areas and community kitchen, creating built-in workstations and study spaces. Meanwhile, on the top level, final touches are being added to the event pavilion and indoor urban farm area, including hardware and wall-mounted equipment, ahead of the final painting stage. |
![]() |
October 10, 2025: Toronto Skyline – Enjoy the view of the city from the George and Martha Butterfield Rooftop Farm.Ìý |
![]() |
October 3, 2025:ÌýPhotos from members of our community!
|
![]() |
September 24, 2025: Exterior work is ongoing along Devonshire Place, with progress being made on pathways and building connections. Once complete, this work will provide direct barrier-free access to the Gerald Larkin Building, George Ignatieff Theatre (GIT) and Lawson Centre for Sustainability, while also creating a fully enclosed route linking the buildings. These improvements will significantly enhance accessibility and connectivity across the College campus. Photos: work continues on grading the landscape for the main entrance areas of the (left) GIT and (right) Lawson Centre for Sustainability. |
![]() |
September 18, 2025: The Whiteside House: Residence – East Wing of the Lawson Centre for Sustainability has been thoroughly cleaned in preparation for final inspections by Trinity and the architectural consultant. Appliances are being installed in the Whiteside House residence lounges, bringing us one step closer to welcoming residents! Images: One of the residence lounges with full kitchen: THEN (left: render by Mecanoo) and NOW (right: September 17, 2025). DYI: there are designated residence lounges with full kitchens on every floor of each wing of residence, as well as multi-purpose study and activity spaces. |
![]() |
September 5, 2025: The Academic Courtyard (between the west wing and the Gerald Larkin Building) is nearing completion, with all major groundwork now finished. Underground heating, concrete paving and final grading have been fully installed, and grass sowing is complete. Tree protection measures have also been removed, preserving a mature maple tree that has successfully weathered the construction process. This resilient tree now anchors the space, offering shade and character to a courtyard designed as a quiet, reflective retreat. As part of a growing network of diverse outdoor spaces on campus, the courtyard will provide a peaceful setting for rest, study and connection with nature. Images: THEN (left: render by Mecanoo) and NOW (right: on August 21, 2025). |
January 2023 to May 2025: The solar-powered camera looks westward from Philosopher’s Walk to capture photos of the entire construction site: ÑÇÖÞ³ÉÈËÊÓÆµ proper is on the left (south); the Gerald Larkin Building is on the far left (along Devonshire Place); the construction zone is in the centre (north field and former parking lot); and the U of T Varsity Centre is on the right (north).
|
October 2024 to March 2025 Mass timber installed, and interior & façade work continues
|
|
|
July 2024 to September 2024 Mass timber installation, residence rooms & interior work
|
|
|
April to June 2024 Whiteside House (East Wing)
Nevil Thomas Wing (Centre Wing)
All Locations: Mechanical and electrical fit-out – ongoing. |
|
|
January to March 2024 Foundation work, concrete structures and mass timber
|
|
|
One-Year Timelapse: January 9, 2023 to January 9, 2024 Marking the first year with our solar-powered camera! View the timelapse video of the construction site (Jan. 9, 2023 to Jan. 9, 2024): from preliminary excavation, geothermal drilling, site servicing work, and installation of rainwater cistern, to cranes assembly, bulk excavation, foundation work across building footprint, pouring of concrete structures to the first delivery of mass timber!Ìý (Content warning: this video contains flashing images as part of the timelapse) |
|
|
October to December 2023 Excavation, foundation work & concrete structures
|
|
|
View our Progress over the First Year of Construction: Fall 2022 to September 2023 |
|
|
July to September 2023 Bulk excavation and foundation work across building footprint
|
|
|
April to June 2023 Site servicing work completed, cistern installed and cranes assembled
|
|
|
January to March 2023 Preliminary excavation, geothermal drilling & site servicing work
|
|
|
October to December 2022 Mobilization & Site Preparations
|
View Construction Updates